⚡ TL;DR
Türkiye had about 250 MW of data center capacity at the end of 2025, according to figures cited at Google Cloud Day Türkiye, and the government’s goal is at least 1 GW by 2030, backed by roughly $3bn of public support intended to unlock $10bn of private investment. The HIT-30 programme offers a $1.5bn data center call (minimum 30 MW, PUE 1.4 or lower) and a $1.6bn AI/cloud call. Flagship projects are clustering in Ankara’s Başkent OSB: Turkcell and Google Cloud’s $3bn hyperscale region (service from 2028), Rönesans and Digital Realty’s campus (groundbreaking October 2026; about $4.1bn over three phases with tenants) and Türk Telekom’s third large data center. Istanbul still hosts 33 of the country’s 81 data centers, and Rönesans plans a 120 MW Istanbul campus. Data localisation rules for banks and personal data underpin domestic demand.

Türkiye’s data center market is small by global standards but is entering its first hyperscale investment cycle, driven by data-localisation rules, the arrival of a Google Cloud region and a new state incentive programme. This guide, part of the Kurums Data Center Economy hub, covers current capacity, the main operators and projects in Istanbul, Ankara and İzmir, the HIT-30 incentives, the regulatory framework and the energy question. For regional context, compare it with the European FLAP-D and Nordic markets and the Gulf data center race.

Key Takeaways

How much data center capacity does Türkiye have?
Around 250 MW at the end of 2025, according to figures cited by officials at Google Cloud Day Türkiye in November 2025. The national target is at least 1 GW (1,000 MW) of installed capacity by 2030.

Who are the biggest investors?
Turkcell with Google Cloud ($3bn hyperscale region in Ankara), Rönesans Holding with Digital Realty (Ankara and Istanbul campuses), Türk Telekom, Trendyol with Castle Investments, and Vodafone Türkiye with DAMAC’s data center arm in İzmir.

What incentives are available?
The HIT-30 data center call has a $1.5bn budget and offers up to 50% tax incentives and energy support of up to 10% of the investment for AI-ready facilities of at least 30 MW with a PUE of 1.4 or lower; smaller projects can use the general incentive regime.

How big is Türkiye’s data center market in 2026?

Türkiye had roughly 250 MW of data center capacity at the end of 2025 and 81 data centers in total, with 33 of them in Istanbul. The government’s target is to quadruple capacity to at least 1 GW by 2030, which would require the fastest build-out in the country’s history.

The 250 MW figure was cited in November 2025, when Google Cloud and Turkcell announced their joint investment at Google Cloud Day Türkiye in Istanbul. An Anadolu Agency summary published in June 2026 listed 81 data centers nationwide: 33 in Istanbul, 13 in Ankara, 10 in İzmir, 8 in Bursa, 4 in Kocaeli, 3 in Denizli, 2 in Gaziantep and one each in nine other provinces including Antalya, Adana, Kayseri, Konya and Trabzon. Most are enterprise or telecom facilities, not hyperscale campuses.

By revenue, the colocation segment is modest. EY-Parthenon Türkiye estimates the colocation market at about $311m in 2023 and $354m in 2024, and projects it reaching about $543m by 2028, growth of roughly 12% a year, faster than the 6% pace of 2019–2023. Demand is rising quickly: EY-Parthenon expects Turkish data traffic to grow from 72 exabytes in 2023 to 310–350 exabytes by 2029. The gap between fast-growing data use and limited local capacity is what the new incentive programme is meant to close.

For perspective, 250 MW is smaller than a single large AI campus in the United States. Building 1 GW by 2030 at current global costs, which we cover in how much it costs to build a data center in 2026, implies the tens of billions of dollars in combined facility and IT investment that ministers and developers are now discussing.

What is Türkiye’s 1 GW data center target and how will it be funded?

The Ministry of Industry and Technology aims for at least 1 GW of installed data center capacity by 2030. It plans to use about $3bn of public resources to mobilise around $10bn of private investment in data centers and AI over the same period.

Minister Mehmet Fatih Kacır set out the $10bn goal in February 2026, and a June 2026 programme added detail: at least 2% of public investment programmes are to go to AI projects, investors get a single-window roadmap of up to 30 working days, and the National Data Library is to open at least 2,000 public datasets. The ministry also wants to spread data centers to secure regions of Anatolia rather than concentrating everything in Istanbul and Ankara.

Industry voices want more. At the October 2026 groundbreaking of the Rönesans–Digital Realty campus, Rönesans honorary chairman Erman Ilıcak proposed raising the national target to 2,000 MW, saying his group could deliver around 600 MW of it, and set an ambition for Türkiye to become Europe’s fifth-largest data center hub after France, Germany, the UK and the Netherlands. Fuat Oktay, chair of parliament’s foreign affairs committee, suggested the target could reach 2,000–3,000 MW. These are aspirations, not policy, but they show how quickly expectations have moved.

How do Türkiye’s HIT-30 data center incentives work?

HIT-30 is Türkiye’s high-technology investment programme, launched in July 2024. Its data center call, announced on 17 October 2025, has a $1.5bn support budget, and a separate HIT-AI call has a $1.6bn budget for cloud-based AI infrastructure.

According to a January 2026 legal summary by Çakmak Avukatlık Bürosu, full support under the HIT data center call requires a minimum of 30 MW of IT capacity, at least 50% of capacity compatible with AI hardware, a maximum PUE of 1.4, and integration with major cloud or AI service providers. Projects that meet only some criteria can receive partial support. Benefits include tax incentives of up to 50%, energy support of up to 10% of the investment, and employment support. The minimum fixed investment under HIT-30 is 2 billion lira.

Smaller projects use the general incentive decree (No. 9903). It requires TS EN 50600 certification at availability class 3, a PUE no higher than 1.65 at full load, fibre from at least two telecom operators, and minimum installed power of 3 MW for the Priority Investments scheme or 500 kW for the Target Investments scheme. Benefits include customs duty and VAT exemptions, corporate tax reductions, interest support and land allocation. The general application window runs to the end of 2030.

💡 Pro Tip: For foreign operators, the HIT-30 thresholds effectively define what the state wants: AI-ready, 30 MW-plus campuses with efficient cooling. A project designed around direct-to-chip liquid cooling, explained in our data center cooling guide, will find the PUE 1.4 test easier to pass and qualify for the higher support tier.

Who are the main data center operators in Türkiye?

The market is led by the two largest telecom groups, Türk Telekom and Turkcell, alongside Vodafone Türkiye, carrier-neutral players such as Equinix and NGN, and newer entrants including Rönesans Holding with Digital Realty and Trendyol with Castle Investments.

Türk Telekom runs large facilities in Istanbul (Esenyurt and Gayrettepe) and Ankara (Ümitköy), according to Sabah, and has laid the foundation for a third large data center at Başkent OSB in Ankara. At a September 2026 investor meeting reported by Bloomberg HT, management said capacity was struggling to keep up with demand, that the company had 10-year customer visibility, and that a framework for data center services with Oracle was under negotiation, with Meta also showing interest. Türk Telekom has also reported successful tests of liquid immersion cooling and promotes a sovereign AI model.

Turkcell has invested about €585m in data centers to date, according to Habertürk, and is now building Türkiye’s first hyperscale cloud region with Google Cloud. It is also expanding its own renewable generation from 63 MW to 200 MW, with a $240m commitment to solar and wind plants, so that data center growth is backed by in-house power.

Vodafone Türkiye opened the first phase of its İzmir data center with DAMAC Digital in September 2026, a $100m project according to Posta (an earlier Anadolu Agency summary cited $150m for the İzmir build), and is adding capacity in Ankara. NGN agreed in October 2026 to host global companies’ data for France’s Orange at its Star of Bosphorus facility, backed by $40m of green financing from Yapı Kredi and Garanti BBVA. Equinix has an Istanbul presence and a Türkiye general manager who spoke at Data Center Eurasia 2026.

Project Partners Location Capacity Investment Timing
Hyperscale cloud region Turkcell + Google Cloud Başkent OSB, Ankara (3 sites) Not disclosed $3bn ($2bn Google, $1bn Turkcell) Service from 2028
Ankara campus (3 phases) Rönesans + Digital Realty Temelli, Başkent OSB, Ankara Phase 1: 22 MW+; up to 200 MW long term ~$4.1bn incl. tenants (Phase 1: $450m + $900m IT) Groundbreaking Oct 2026; Phase 1 in 2028
Istanbul campus Rönesans + Digital Realty Deliklikaya, Istanbul 120 MW $1.7bn Rönesans; $5.2bn incl. tenants Foundation stone planned for February
Ankara Data Center Trendyol + Castle Investments Ankara 48 MW $500m (first phase) First section planned Q3 2026
İzmir Data Center Vodafone Türkiye + DAMAC Digital İzmir Not disclosed $100m Phase 1 opened Sep 2026
Third large data center Türk Telekom Başkent OSB, Ankara Not disclosed Not disclosed Foundation laid

Source: Habertürk; Anadolu Agency via Foreks (19 Oct 2026); Webtekno; Posta; Bloomberg HT; Sabah (2025–2026). Investment totals include tenant/partner IT spending where stated.

Why is Ankara becoming Türkiye’s hyperscale hub?

Ankara’s Başkent Organized Industrial Zone has become the site of choice for the three largest new projects: Turkcell and Google Cloud, Rönesans and Digital Realty, and Türk Telekom. The capital offers land, power connections, lower seismic risk than Istanbul and proximity to government and defence customers.

The Turkcell–Google Cloud region will consist of three separate, redundant sites, the first at Başkent OSB, and is expected to start service in 2028. Google described it as one of its hyperscale data centers worldwide and Türkiye’s first hyperscale cloud region; Turkcell’s CEO said the investments could add $5bn a year to the economy. The Rönesans–Digital Realty Ankara campus broke ground in Temelli on 19 October 2026 with Minister Kacır attending. Its first phase will deliver more than 22 MW of IT capacity on about 10,000 square metres, with $450m for buildings and infrastructure and a further $900m expected from service providers for technology; Digital Realty said Türkiye is one of its new markets this year alongside Milan, Sofia, Lisbon and Kuala Lumpur.

Speakers at that ceremony stressed Ankara’s role as a production and defence hub, home to all five Turkish defence firms in the global top 100. For defence, public sector and regulated finance customers, a domestic hyperscale region solves a long-standing problem: they could not use foreign cloud regions for many workloads, and local enterprise facilities lacked the scale and service range of global cloud platforms.

What role does Istanbul still play?

Istanbul remains Türkiye’s main interconnection and enterprise market, with 33 of the country’s 81 data centers and most carrier-neutral facilities. It is where international networks, financial institutions and content providers meet.

Rönesans plans a 120 MW campus at Deliklikaya in Istanbul with Digital Realty, with $1.7bn of its own investment and $5.2bn in total once tenants and partners are included. NGN’s Star of Bosphorus deal with Orange shows Istanbul’s potential as a regional hosting point for multinational data. Türk Telekom’s two largest Istanbul facilities and Equinix’s presence anchor the interconnection ecosystem.

The constraints are land costs, grid capacity in dense districts and seismic risk, which pushes operators to geographic redundancy between Istanbul and Ankara. Our site selection guide explains how operators weigh latency against power, land and hazard exposure.

⚠️ Risk: Most announced capacity is still on paper. Türkiye would need to add around 750 MW in five years, roughly three times what it built over the previous decades. Delays in grid connections, lira volatility that raises the cost of imported equipment, and dependence on a few anchor tenants could push projects back. Long transformer and switchgear lead times, covered in our power bottleneck guide, apply here too.

How do data localisation rules drive demand in Türkiye?

Turkish rules on banking systems and personal data push regulated organisations to keep data and core systems inside the country. That creates steady domestic demand for local capacity and is a key reason hyperscalers are building in-country regions rather than serving Türkiye from Europe.

Banks are subject to information-systems rules from the Banking Regulation and Supervision Agency (BDDK), which require primary and secondary systems to be located in Türkiye. Payment and e-money institutions face similar expectations. The personal data protection law (KVKK) was amended in 2024 to replace its strict explicit-consent approach to cross-border transfers with a framework closer to Europe’s GDPR, including standard contracts. This has made foreign cloud use easier for some workloads, but many public sector, finance and critical-infrastructure users still prefer or are required to use domestic facilities.

Industry participants told Ekonomi Gazetesi that customers increasingly choose data centers based on where data is stored, how it is protected and regulatory compliance, not only on capacity. Banking, finance and public bodies emphasise local storage, security and uninterrupted service. That gives Türk Telekom, Turkcell and the new local hyperscale regions a structural advantage.

Is energy a constraint for Turkish data centers?

Energy is the critical variable. Türkiye has expanding renewable capacity but relies on imported gas for part of its power, and electricity costs and grid connection times will determine whether 1 GW is realistic. The state is addressing this with energy support of up to 10% of investment under HIT-30.

Operators are hedging by building their own generation. Turkcell’s move from 63 MW to 200 MW of renewable capacity and Türk Telekom’s $300m solar programme, reported by Bloomberg HT, both aim to secure power and green credentials for data center customers. Efficiency requirements (PUE 1.4 for HIT-30 support and 1.65 under the general decree) push new builds toward modern cooling. Global hyperscalers also have their own carbon goals, discussed in our article on data center sustainability and 24/7 clean energy.

Some Anatolian provinces are pitching natural advantages. Officials have highlighted plans in Nevşehir, in Cappadocia, to convert rock-carved cold stores into data centers, claiming investment and operating costs around 45% lower than in Istanbul and Ankara. Such projects are small, but they fit the ministry’s goal of distributing capacity across secure regions.

Announced Turkish data center projects (total investment, $bn)Rönesans-DR Istanbul (incl. tenants)$5.2bnRönesans-DR Ankara (incl. tenants)$4.1bnTurkcell + Google Cloud$3.0bnHIT-AI call (public support)$1.6bnHIT data center call (public)$1.5bnTrendyol + Castle (phase 1)$0.5bnVodafone + DAMAC Izmir$0.1bnPublic call budgets are support envelopes, not project spending.
Announced project investments and public incentive budgets in Türkiye. Sources: Anadolu Agency (Oct 2026), Habertürk, Milliyet, Webtekno, Posta. Project totals with tenants include partner IT spending.

What is the outlook for Türkiye’s data center market to 2030?

If announced projects are delivered, Türkiye could reach the 1 GW goal close to 2030, with Ankara emerging as the hyperscale hub and Istanbul as the interconnection centre. The key tests are whether the Google region opens on time in 2028 and whether more global cloud and AI companies follow.

Bulls point to a large domestic market, data localisation, a strategic location between Europe, the Middle East and Central Asia, and incentives that are generous by European standards. Bears point to lira volatility, energy import dependence, seismic risk and competition from Gulf states with cheap power and sovereign capital. Türk Telekom’s talks with Oracle and Meta’s reported interest suggest that more hyperscale demand could arrive if capacity is available.

For investors, the opportunity is less about immediate scale and more about first-mover positions in a market moving from enterprise colocation to hyperscale. Compare the Turkish model, where telecom operators and construction groups partner with global firms, with India’s conglomerate-led build-out and the ownership structures described in our private equity platforms guide.

Frequently Asked Questions

How many data centers are there in Türkiye?

An Anadolu Agency summary in June 2026 counted 81 data centers: 33 in Istanbul, 13 in Ankara, 10 in İzmir, 8 in Bursa, 4 in Kocaeli, 3 in Denizli, 2 in Gaziantep and one in each of nine other provinces. Total capacity was about 250 MW at the end of 2025, with a national target of at least 1 GW by 2030.

When will the Google Cloud region in Türkiye open?

The Turkcell and Google Cloud hyperscale region is expected to begin service in 2028. It will comprise three redundant sites, the first in Ankara’s Başkent Organized Industrial Zone. Google is investing about $2bn and Turkcell about $1bn, making it a $3bn project and Türkiye’s first hyperscale cloud region.

What incentives does Türkiye offer for data centers?

The HIT-30 data center call has a $1.5bn budget and offers up to 50% tax incentives plus energy support of up to 10% of investment for AI-ready facilities of 30 MW or more with a PUE of 1.4 or lower. Smaller facilities can use the general incentive decree, with customs duty and VAT exemptions, tax reductions and land allocation.

Do Turkish banks have to store data in Türkiye?

Yes. BDDK rules on banks’ information systems require primary and secondary systems to be located in Türkiye, and payment institutions face similar requirements. KVKK’s 2024 amendments eased cross-border personal data transfers, but regulated sectors and public bodies still create strong demand for domestic data center capacity.

Sources: Anadolu Agency via Foreks and Milliyet (2026); Habertürk (Turkcell–Google Cloud, Nov 2025 and Mar 2026); Ministry of Industry and Technology HIT-30 announcements; Çakmak Avukatlık Bürosu, Türkiye’de Veri Merkezi Yatırımları (Jan 2026); EY-Parthenon Türkiye data center study; Bloomberg HT (Türk Telekom, Sep 2026); Sabah; Webtekno (Trendyol); Posta (Vodafone, NGN); Ekonomi Gazetesi.
Last Updated: November 2026 · Reviewed by the Kurums Technology editorial team. Figures are as reported by the cited sources at the time of writing; capacity, capex and deal figures change quickly — verify before acting.

Discover more from Kurums | Business Intelligence

Subscribe to get the latest posts sent to your email.

Discover more from Kurums | Business Intelligence

Subscribe now to keep reading and get access to the full archive.

Continue reading