FERC’s six large-load show-cause orders are dated 18 June 2026, not 19 November as our morning briefing said. What happened this week is the next stage: after a 90-day pause, PJM, MISO, CAISO and NYISO filed their tariff proposals on 16 November and ISO-NE on 13 November. The filings put numbers on things buyers negotiate: 10 to 20-year minimum revenue commitments backed by credit support, non-refundable application fees, and cheaper non-firm service that is interrupted at set price levels. Nothing is in force until FERC rules, and the earliest requested effective dates fall in January to March 2027.
For anyone buying power for a data centre, signing a colocation lease or choosing a site, the question has moved from what FERC wants to what each grid operator has now proposed to charge and require.
Our Notes briefing summarised the orders. This analysis corrects its timeline and works from the PJM order text, two PJM filings and trade coverage of the responses.
This is not legal or regulatory advice. Every tariff described here is a proposal that FERC may accept, change or reject.
What happened, and what the coverage adds
First, the correction. The order to PJM that we read, 195 FERC ¶ 61,211 in Docket No. EL26-67-000, is marked “Issued June 18, 2026”. The briefing’s 60-day and 30-day deadlines are real, but they ran from June: the generation-adequacy reports were due in July and the responses in mid-August. We found no show-cause order dated 19 November. FERC’s own news pages blocked our requests, so we rely on the order as posted by PJM, law-firm summaries and press reports.
The order let operators ask for a pause of up to 90 days to prepare tariff filings under Federal Power Act section 205. PJM’s 16 November filing cites a FERC letter order of 14 August 2026 that suspended its duty to respond if it filed by 16 November. Utility Dive reports that PJM, MISO, CAISO and NYISO filed on 16 November and ISO-NE on 13 November, and that SPP was due by 20 November. POWER magazine said on 19 November that SPP had not yet filed. We could not confirm whether it has since.
Details the briefing did not have:
- Dockets. Holland & Knight lists them as EL26-67 (PJM), EL26-68 (SPP), EL26-69 (NYISO), EL26-70 (MISO), EL26-71 (CAISO) and EL26-72 (ISO-NE).
- All five commissioners wrote separately. Chairman Laura Swett said the orders find the status quo “is not good enough”. Commissioner David Rosner said cost recovery agreements make large loads pay “regardless of whether the large load comes online as planned”. Commissioner David LaCerte warned that an insufficient filing “will result in the Commission dictating the solutions for you”. Commissioner Judy Chang noted that FERC “does not pursue the broad assertion of jurisdictional authority” in the Energy Department’s proposal.
- The Energy Department link. The orders draw on comments filed after Energy Secretary Chris Wright’s October 2025 advance notice of proposed rulemaking, Docket No. RM26-4. POWER reports that docket remains open.
- PJM co-location is separate. Co-located load in PJM is handled in Docket No. EL25-49, where FERC issued a further order on the same day in June.
- Existing deals. The order says the proceeding “is not intended to disrupt existing commercial arrangements, but rather to establish prospective reforms”, and asks for effective dates that leave time to finish agreements nearing completion.
What Google Trends shows
We compared five terms in the United States. “Data center” dominates: it peaked at 100 on 18 September and averaged 59.1 over the first 60 days against 47.7 over the last seven. Its last five daily readings were 57, 56, 55, 50 and 36; the final day may be incomplete. It is a broad term, so it says little about this proceeding.
The regulatory terms barely register. “FERC” peaked at 3 on 21 September and averaged 1.0 over the last seven days. “PJM” peaked at 5 on 13 and 14 October. “Large load interconnection” read 0 on every day but one. The 16 November filings produced no visible rise. Rising queries include “pjm data center power proposal”, “ferc rejects pjm data center proposal” and “phantom data center power demand”; we did not investigate what the second refers to.
The cost-allocation mechanics: who signs, and who pays
FERC’s central tool is a pro forma cost recovery agreement. In the PJM order it is a three-party contract between the grid operator, the transmission owner and the “Eligible Customer taking transmission service on behalf of a large load”, which RMI describes as the host load-serving entity. The data centre is usually not a party. The agreement would require a “minimum contribution” to the transmission owner’s revenue requirement if the load “does not materialize as planned or is not developed at all”, sized on the megawatts of service requested and backed by credit support.
Two points matter for buyers. FERC said credit support already posted by a large load under a retail agreement may be counted, to avoid duplication. And it said it does not intend to alter existing regional cost allocation methods for network upgrades; the aim is to stop stranded costs moving to other customers.
The filings turn this into terms. In an October consultation notice, PJM’s transmission owners said they were considering a term of 10 to 20 years from the start of service, a make-whole charge for any shortfall, and a letter of credit or similar security for the full term. POWER reports the filed PJM version has a minimum 10-year term, recurring commitments of 80% to 100% of a firm-service benchmark and credit support based on 100% of it. For MISO, POWER reports a 20-year revenue commitment for covered network upgrades, a non-refundable $250,000 application fee and a $100,000 study deposit. ISO-NE proposes an exit fee based on remaining net book value.
These terms are contested. RTO Insider reports that MISO state regulators find its cost-shift plan inadequate, and that the NEPOOL Participants Committee did not support the New England transmission owners’ cost recovery approach. We read only the summaries of these paywalled articles.
Five filings, five designs
The following is drawn from POWER, Utility Dive, PJM and ISO-NE.
- PJM. A “Fast Energization” process would study generation and large-load transmission requests together and, PJM says, cut the timeline from two years to one. Readiness and financial requirements move earlier. POWER reports the first cycle is expected in late November 2027. PJM’s Large Load definition, already accepted with effect from 12 October 2026, is 50 MW or more at a single electrical site, counting affiliated facilities within one mile. A separate filing (ER27-522) sets ride-through duties for “Large Computational Loads” from 16 January 2027.
- MISO. Three Large Load Project Review cycles a year, with a first application deadline of 1 March 2027. Non-firm service under its new product would be interrupted when the local price exceeds $100/MWh; MISO says that allows service in more than 95% of hours. Implementation would be no earlier than 1 January 2029.
- ISO-NE. Firm, interim and non-firm contract demand services. Firm service carries a “bring your own new capacity” requirement. Interim and non-firm customers would be re-dispatched when local prices reach $250/MWh, which ISO-NE says occurs in about 1% of hours. Facilities operating or sufficiently under construction on 18 June 2026 are exempt.
- NYISO. Firm and Non-Firm Withdrawal Service, a grouped study process of about 18 to 24 months, and 15-year terms for co-located and partner-resource arrangements.
- CAISO. A Flexible Interim Load Interconnection option with project-specific operating limits, transmission-owner-led studies, and most reforms requested from 16 February 2027.
POWER cautions that the three price triggers work through different mechanisms and are not directly comparable.
Contract terms to revisit
- Colocation power pass-throughs. If the utility must guarantee 10 to 20 years of transmission revenue and post security, expect it to seek the same from the operator, and the operator from tenants. Check whether your lease lets the landlord pass through minimum-demand charges, shortfall payments or collateral costs, and whether your term is shorter than the commitment behind it.
- Curtailment and service levels. Non-firm and interim service is cheaper because it is interrupted first. Ask which service a site holds. PJM describes its ride-through rules as keeping data centres connected “rather than switching to backup generation”, which affects resilience design.
- Power purchase agreements. Co-located and “bring your own capacity” structures tie a load to a specific generator for long periods. Check tenor, change-in-law and what happens if the transmission service is downgraded or delayed.
- Deposits and milestones. Treat application fees as sunk. Check who bears forfeited deposits if a site is dropped.
- Grandfathering. PJM’s transmission owners said in October they were considering keeping existing agreements with comparable protections. Do not assume it.
A playbook for procurement teams
- Correct your tracker. The live dates are comment deadlines and requested effective dates, not a new 60-day clock.
- Sort sites by region and size. The common threshold is 50 MW, but definitions differ.
- Ask each utility and colocation provider which service it expects to hold and what security it expects to post.
- Model two cases for new sites: firm service with a long minimum commitment, and non-firm service with interruption at the proposed triggers.
- Add clauses now on tariff change, pass-through caps and curtailment credits.
- Decide whether to comment, with counsel.
More coverage is on the Kurums Procurement and Procurement News pages.
What to watch next
- Comment deadlines. The order allows responses within 30 days of the filings, which by our arithmetic is mid-December. PJM has asked for 60 days and a ruling within 120. Check each docket’s notice.
- SPP’s filing, which we could not confirm.
- FERC’s rulings, and whether it accepts regional differences or imposes its own terms.
- PJM’s capacity auction. Utility Dive reports consumer advocates from several states asked PJM to delay the auction set for 9 to 15 December until speculative data-centre load is removed from the forecast. PJM said a delay “could destabilize the market”.
- State action. Commissioner Lindsay See told Utility Dive that states have had “blind spots” about which customers drive transmission costs.
Frequently asked questions
Did FERC issue new orders on 19 November 2026?
Not show-cause orders that we could find. The six are dated 18 June 2026; the November news is the responses.
Do the proposals change contracts already signed?
FERC said the proceeding is meant to be prospective. How each filing treats agreements in progress varies, so check the region. ISO-NE, for example, exempts facilities sufficiently under construction on 18 June 2026.
Will our data centre sign the cost recovery agreement?
Under FERC’s preliminary design, usually not. The utility taking transmission service signs, and the cost reaches you through your retail or lease contract.
Is non-firm service worth considering?
It may connect sooner and cost less. POWER reports an illustrative PJM non-firm rate cap 35.3% below the firm rate. The price is interruption, so it suits loads with real flexibility or on-site supply.
Sources and further reading
- FERC, Order Instituting Proceeding, PJM Interconnection, Docket No. EL26-67-000, issued 18 June 2026 (as posted by PJM, with the five concurrences).
- PJM: 16 November 2026 filing, Docket No. ER27-522-000; Inside Lines on Fast Energization; Transmission Owners’ consultation notice, 9 October 2026.
- Utility Dive: Grid operators file closely watched large load interconnection reforms at FERC (17 November 2026).
- POWER: Five Grid Operators Respond to FERC With Distinct Plans for Large-Load Integration (19 November 2026).
- ISO Newswire: ISO-NE files proposal with FERC to address ‘large loads’.
- Utility Dive: interview with Commissioner See and PJM urged to delay base capacity auction.
- RTO Insider (summaries only, paywalled): MISO response, MISO state regulators, NEPOOL vote.
- Background on the June orders: RMI, Holland & Knight, Capacity on the abeyance requests.